Project Details
Property Name:
House of Dignity
Property Address:
585 8th St, Oakland, CA, USA
Completion Date:
November 2023
Major Equipment Installed
The following equipment was installed as part of this project:
Category | Make/Model | Type | Qty | Unit | Location Installed | Area Served |
---|---|---|---|---|---|---|
Low Flow | Low Flow Aerators & Showerheads | Low Flow | 24 | Bathrooms | Bathrooms | |
Lighting | Various | LED Lighting | 249 | Whole Building | Whole Building | |
HVAC | Gree GMV Heat Pump | Heating & Cooling | 2 | Courtyard | Whole Building | |
Hot Water | ECO2 Systems GS4-45HPC-US | Water Heater | 4 | Courtyard | Whole Building |